Work-package NoWorkpackage titleLead contractor NoStart monthEnd monthDeliverable No
WP1Project administrative and technical managementGRNETM0M29D01, D08, D11, D18
WP2Requirements studies, analysis and baseline designGRNETM0M3D04, D05
WP3Procurement and network designGRNETM1M5D06, D07
WP4Network implementation and operationROEDUNETM4M29D09, D12
WP5Services & tools deployment and configurationNIIFIM6M29D13, D15
WP6Training, dissemination and communicationTERENAM0M9D02, D03, D10, D14, D16, D17
 
 